The Chain / Node 03 of 8 / Storage, origin
Node 03 · The Origin

Origin storage, the buffer before the ship.

Tankage at the production hub that holds synthesised ammonia and methanol between a continuous plant and a discontinuous ship. It decouples a plant that runs every hour from vessels that call every few weeks.

Node status
Indicative
Costed inside the project CAPEX in the Dakhla build, not yet isolated as its own sized model. Figures below are indicative.
Input
Synthesised productAmmonia and methanol from the production node, arriving continuously
Output
Buffered productHeld ready for parcel-sized loading onto the next vessel
What it is

Where a continuous plant meets a discontinuous ship.

The electrolyser and synthesis loops run around the clock. The vessels that carry the product north do not; they arrive in parcels, on a cadence measured in weeks. Origin storage is the tankage that absorbs the difference: refrigerated tanks for ammonia, ambient tanks for methanol, sized so the plant never has to throttle because a ship is late and a ship never waits at berth because the tank ran dry.

This is the mirror of the destination buffer, on the production side of the water. The destination node holds landed tonnes against downstream draw; this node holds freshly made tonnes against ship arrival. The two are the same physics with the demand inverted, which is why the storage cost ratios carry across and the refrigeration premium on ammonia shows up here as well.

Inputs & assumptions

What drives the node.

ParameterValueBasis
Throughput, ammonia150 kT/yrDakhla build output P
Throughput, methanol500 kT/yrDakhla build output P
Buffer duration~14 daysDesign basis, set by ship cadence and parcel size D
Ammonia tankage~8,500 m³14 days at 150 kT/yr, refrigerated, 0.68 t/m³ D
Methanol tankage~24,300 m³14 days at 500 kT/yr, ambient, 0.79 t/m³ D
Refrigeration premium~2.25×Refrigerated ammonia vs ambient methanol, per m³ E
MMeasured
PProject-grade
EEstimate
DDesign
Outputs & economics

What the node costs, indicatively.

Indicative
Node status
~14 days
Buffer, design basis
~$17M
Order, by analogy
In project
Where it sits today

On a like-for-like 14-day buffer at the same throughput, origin tankage lands at roughly the same order as the destination node, near $17M, dominated by the same refrigerated-ammonia premium. That figure is an analogy, not a sized result. In the Dakhla build it is not broken out as a line; it sits inside the on-site infrastructure and process-plant CAPEX rather than as an isolated node cost.

Node finding

Real cost, not yet isolated.

Origin storage is the one node in the chain that is fully real in the project but not yet modelled as its own unit. The tankage exists in the Dakhla design and its cost is carried inside the build total, but it has not been pulled out, sized and stress-tested the way the transport, delivery and destination-storage nodes have.

Why it stays indicative

Isolating this node honestly means committing to a buffer duration, and that number is a live design choice, not a default. A longer buffer protects the plant against late or missed ships but ties up tankage CAPEX and working capital in standing inventory; a shorter one is cheaper but raises the risk of a forced production cut when a vessel slips. Because that trade sits against the ship cadence in the corridor module, the node will be isolated once the loading cadence is fixed, rather than asserted now with a buffer number chosen to look tidy. Holding it as indicative is the disciplined position, not a gap left by accident.

Provenance & sources

Where the numbers come from.

Throughput (150 kT ammonia, 500 kT methanol): the Dakhla Phase 1 build outputs, project-grade.

Tank volumes (~8,500 m³ ammonia, ~24,300 m³ methanol): derived at a 14-day buffer and liquid densities of 0.68 t/m³ ammonia and 0.79 t/m³ methanol. Design-stage, and contingent on the buffer duration being confirmed.

Indicative CAPEX (~$17M): carried across by analogy to the destination storage node at the same throughput and buffer, using $900/m³ refrigerated and $400/m³ ambient. Not a sized origin result.

Currently inside the project CAPEX (Sim 3). Not isolated as its own model. Indicative, modelled by analogy, not achieved.

Independence

How this node stands alone.

Even held as indicative, the node has a clean interface. It takes continuous production on one side and releases parcels to the ship on the other, and it commits to neither the plant that fills it nor the vessel that empties it.

Connects upstream to
The production node
Receives synthesised ammonia and methanol as they are made. Any synthesis plant of the same throughput fills this tankage; the storage operator need not own the plant.
Connects downstream to
The transport node
Releases parcel-sized batches to whatever vessel calls. Because the node is carrier-agnostic, the same buffer serves a chartered ship or an owned newbuild without change.
Go deeper

Where it lives today.

Inside the project
Dakhla build & Project Finance · Sim 3
Until this node is isolated, its cost sits inside the Dakhla build CAPEX and the project-finance model. The Dakhla page shows the build total this tankage is folded into.
See the Dakhla build